Construction Schedule
The construction contract was awarded to Corman Construction, Inc. of Annapolis Junction, Md., and work began in April 2004. Weather permitting, work will be complete late summer 2006.
Notice to Proceed Issued
|
04/05/2004
|
Incentive Start (Max.Date)
$5,000 per day/max of $200K
|
06/11/2006
|
Incentive/Disincentive
Cross Over Date
|
07/21/2006
|
Disincentive Start
$5,000 per day/no maximum
|
07/22/2006
|
Liquidated Damages+Disincentive Start
$5,000 + $3030/per day, no maximum
|
08/10/2006
|
|