Project Activity
|
Brief Description
|
Anticipated Allotted
Time by SHA
|
Environmental Documentation
|
NEPA, Section 106, Section 4 (f) requirements
|
Concurrent with design
(4 months for Categorical Exclusion approval)
|
Bridge and/or Structure review
|
TS&L, Boring, Structural and Foundation review
|
Concurrent with design
(4 weeks/review)
|
PI or Semi-final Review
(if applicable)
|
|
Concurrent with design
(4 weeks/review)
|
Final Review
|
90-95% complete plans and specification proposal book with all required permits and approval letters
(Checklist provided at kick-off meeting)
|
Concurrent with design
(4 weeks/review)
|
"Request to Advertise"
|
100% complete plans and proposal book with all required permits and approval letters
(Checklist provided at kick-off meeting)
|
5 weeks
|
Advertisement to Bid opening
|
|
3 weeks minimum
|
"Concurrence to Award"
|
Signed proposal book and forms
(Checklist and forms provided at Bid openings
|
5 weeks
|